Yet another planning application!.......

TOWN AND COUNTRY PLANNING (Development Management Procedure) (England) Order 2015 SITE NOTICE – under Articles 15, 33 & 34 and Schedule 3 of application for planning permission APPLICATION NO.

 1/0939/2025/FULM 
PROPOSAL : Proposed Battery Energy Storage System (BESS) with an import/export capacity of up to

 99.4MW 
including associated infrastructure, engineering works, drainage, cabling, landscaping and access LOCATION : Land At Grid Reference 249487 125686 Woodtown East The Water Devon APPLICANT : CO Agent

Objection to Bideford BESS fromThe Rt Hon Sir Geoffrey Cox KC MP



objection to planning application by a close neighbour to the site.

We are one of the two existing properties closest to, and most impacted by, this proposed development.  We object to this proposal in the strongest possible terms for the following reasons:

1. This is a significant infrastructure plan which proposes the industrialisation of over 10 acres of high quality farmland currently used for grazing.  For a plan of this size and impact, the consultation period was far too short and not properly completed.  The face-to-face presentation by Enray took place after this application was submitted meaning any valid challenges or questions raised have been ignored – we have a list of 18 questions given to Enray during that meeting which have yet to be answered.The application itself is clearly deliberately misleading and does not include vital information such as the total energy storage capacity, lifetime of the BESS and frequency of battery replacements or repairs.  Misleading information around the number of homes this would service is provided, with no evidence to back up these claims.  The claim that over 20,000 tonnes of CO2 would be offset annually fails to consider the CO2 impact during manufacture in and transportation from China.  The Planning Design and Access Statement (PDAS) says 50 storage containers are planned in paragraph 3.9 but paragraph 3.10 shows 60 containers.  The PDAS does not reflect the latest National Fire Chiefs Council guidance.  The Landscape and Visual Impact Assessment fails entirely to take into consideration the impact to the nearest 2 properties and focuses on the visual impact to farm leasing its own land for this proposal.  The impact from the north west and south west needs to be considered as well as the impact visually to existing properties Five Acre and Webbery Cross Cottage.  Those images provided clearly demonstrate the negligible effect of the screening proposed for this development which is clearly not suitable in any attempt to disguise the industrialisation of this 10 acres of Devon countryside

2. This area is quite literally under siege from renewable energy related plans (solar, wind and BESS) and we already have our fair share - there should be no further adverse impact to the countryside in this Parish.  The details in the PDAS are now out of date now that the results of the National Energy System Operator (NESO) connections reform have been published.  This has shown that we have over 4 times the amount of “shovel ready” projects to fulfil Clean Power 2030 (CP30) targets including 3 times the amount of BESS required.  There is already a BESS facility approved at Gammaton some 600m to the south of our property and an application for a BESS facility as part of the Bulworthy Solar Farm was submitted in June of 2025.  Where does it end?  Enray themselves admit this in paragraph 2.7 of their PDAS which suggests this area is already “fettered with other energy infrastructure.”  In reality, they are talking about the solar fields further to the south, much closer to the Alverdiscott substation, and their proposal constitutes infill between their and the Bulworthy proposal.  It really is like a Wild West Gold Rush in North Devon currently when it has been clearly demonstrated that enough renewable projects have already been approved to meet near and mi-term requirements.  Contrary to the content of the application, and what Enray were telling us on 10th December last year, this BESS would not have a grid connection for at least 10 years anyway!

3. The Development Plan comprises the North Devon and Torridge Local Plan 2011-2031, of which Policy ST14: Enhancing Environmental Assets seeks to protect and enhance the natural environment of North Devon by ensuring that development contributes to protecting and enhancing local landscape character.  Enray attempt to justify the location of this proposal by claiming a lack of “intervisibility” between proposals which is simply not the case.  We benefit from expansive views to the north, south and west of our property and Webbery BESS and Bulworthy Solar and BESS would both be clearly visible from the same viewpoint

4. There is a well documented and significant fire risk associated with BESS installations.  Any application will attempt to downplay this risk but this proposal would be situated far too close to existing residential properties and businesses for there not to be a substantial and real risk

5. This application will have an enormous negative impact to the amenity of our property, Five Acre, and the field we own to the south of our property, the southerly portion of which sits adjacent to this proposal.  The southern portion of our field is currently used for 6 bee hives with plans to expand this to as many as 20 over the next few years.  Noise during construction of this BESS will disturb the bees, the result of which is likely to be them swarming and leaving our hives to find somewhere quieter to live.  The operational noise of the fans will have a similar impact and the electro-magnetic fields around the battery facility will interfere with the internal navigational functions of the bees, again causing the populations to weaken and potentially move elsewhere.   The viability of our bee hives will be decimated by this proposal and we will separately provide further detail on this.  We have an area in this field that we regularly use to sit and enjoy the surroundings, views and local nature and the amenity of this will be totally destroyed by the adjacent BESS facility if approved.  This will mostly be a result of the noise pollution it will create but it is also likely to be visible from this area as the screening proposed by Enray would be insufficient.  The noise impact to Five Acre and Webbery Cross Cottage will be detrimental to both our health and wellbeing and the noise impact assessment has not satisfactorily taken our property into consideration.  It is impossible to look at a decibel number and understand the impact this will have on us.  The frequency and type of noise is vital and the only way that can properly be understood would be to run a pilot scheme where speakers are set up around the proposed site and the volume and frequency of the BESS installation is replicated over  1 month period.  This would be inexpensive to run and would enable us to understand the aural impact of the proposal rather than just imagining what a number of decibels sounds and feels like.  This was suggested at the face to face meeting on 10th December and it was agreed that this would be a good idea, however it then became clear that the application had already been submitted.

6. The proposed scale of this development will intrude and be at odds with the immediate and surrounding landscape character, and the local built character. By definition, the industrialisation of the countryside on any scale, let alone 10 acres, is at odds with the Torridge and North Devon local plans.

7. It is our understanding that Enray Power have an option on the lease of the whole field situated to the south and west of our property.  We strongly contest the need for the this BESS in the first place but if it is determined that there is a valid requirement for this facility, it should be situated in the furthest south portion of the field, some 240m further south.  This would minimise any visual and noise impact to Five Acre and Webbery Cross Cottage.  Enray have said that they would not be able to utilise this land because of the existence of a scheduled monument (Iron Age enclosure and Roman marching camp) however it is quite clear from Historic England Maps that this monument is located in an adjacent field further west and not under the southern most portion of the leased land.  Moving the proposal here would reduce the possible smoke impact to Webbery Cross Cottage in the event of a fire and dramatically reduce the aural harm to Five Acre and Webbery Cross Cottage.  Were the BESS constructed here, there is a much increased chance our Honey Bee hives remaining viable, although we cannot be certain of this.  This also moves the proposal further away from approved applications 1/0840/2025/FUL, 1/0528/2025/FUL and 1/0935/2025/FUL

 

In summary:

There is no need for this proposal from an energy infrastructure perspective

It would be located far too close to existing residential properties and will have an unacceptable adverse impact to the amenity of the gardens and land of those properties

It will potentially decimate an existing apiary causing financial harm and further reducing amenity of the owners land

The application itself is riddled with flaws, mistruths and inaccuracies

An appropriate and fair consultation period has not taken place

The application would turn 10 acres of highly valuable and prime grazing land into an industrial complex in the middle of the countryside which would therefore be in direct conflict with the local plan

This area already has what could be considered its fair share of renewable proposals and with each additional scheme approved, the landscape character we should be looking to preserve is further permanently damaged.

 

 

Devon CPRE objects to planning application 1/0939/2025/FULM

www.cpredevon.org.uk

PO Box 26, Beaworthy, EX21 5XN Tel: 01392 966737

Registered Charity No: 1175228

Standing Up For Our Devon Countryside

 

 

Proposed Battery Energy Storage System (BESS) with an import/export

capacity of up to 99.4MW including associated infrastructure, engineering

works, drainage, cabling, landscaping and access

Land At Grid Reference 249487 125686 Woodtown East The Water Devon

Devon CPRE

January 2026

1Devon CPRE objects to planning application 1/0939/2025/FULM.

The planning application contains many misleading, incorrect and unsupported

statements. It does not provide any references to the information used to provide many of

the claims made. It does not include important information, such as:

1. 2. 3. The total energy storage capacity of the battery energy storage system (BESS).

The lifetime of the proposed BESS.

The likely frequency of replacement of batteries and inverters.

Section 3 of the Planning, Design and Access Statement (PDAS) describes the proposed

development.

Paragraph 3.3 states that the proposal would have an energy storage capacity of 99.4MW.

This is a false statement. 99.4MW is the proposed battery power capacity. The energy

storage capacity (measured in MWh) is not given.

Paragraph 3.3 also states that the proposal is sufficient to supply electricity to

approximately 39,949 homes annually. This statement is misleading; claiming 5-figure

accuracy is nonsense. No evidence is supplied to support the number. The number of

homes supplied is dependent on the energy storage capacity of the BESS and how

frequently it is charged and discharged. Neither piece of information is provided.

Furthermore, due to round-trip losses of about 10% during a battery charge-discharge

cycle, the proposed BESS will be a net consumer of electricity. Thus overall the effect of

the proposal would be to remove electricity supply from a number of homes. The proposal

would supply a negative number of homes.

Paragraph 3.3 also states that the proposal would offset 20,158 tonnes of CO2e per year.

This is another ridiculousy accurate figure, with no evidence to support it. Does it include

the huge emissions involved in the manufacture and transport of the batteries (no doubt

manufactured in China, where large amounts of coal are used in the manufacturing

process)?

Paragraph 3.9 states that there would be 50 containerised battery units. The layout plans

(see paragraph 3.10) show 60 units.

2Paragraph 2.9 states The nearest residential property is located approximately 100m

north-east of the Site. Other nearby properties are located circa. 130m to the north (Little

Webbery), 150m to the north-west, 262m to the east, and 475m to the north (West

Webbery). The property 100m to the north-east lies in the prevailing wind direction. In the

event of a fire/explosion leading to the release of toxic fumes and vapours the residents of

this property would be in extreme danger. It is well known that smoke from a fire can

travel well over 100m close to the ground.

Paragraph 5.108 references the National Fire Chiefs Council (NFCC) Guidance issued in

November 2022. Since then, much more is known about the risks and consequences of

battery fires/explosions. Consequently a draft issue of the revised NFCC guidance has

been released. The NFCC has also published a position statement on BESS (Battery

Energy Storage Systems - NFCC). The PDAS should be updated to reflect the latest

NFCC guidance and position statement.

1. Paragraphs 6.2 to 6.6 discuss the contribution of the proposed BESS to meeting the

national need for BESS. This section of the PDAS is completely wrong. Paragraph 6.3

states the Applicant has also secured a connection date to the Grid in 2028. However this

date is now irrelevant. The results of the National Energy System Operator (NESO)

connections reform have been issued (Connections Reform Results | National Energy

System Operator). The results have shown that:

The old connection queue total was 700GW, four times what was needed for 2030,

with shovel-ready projects waiting up to 10 years for connection.

For batteries, in the old queue there were about three times too many.

For batteries the new connections pipeline shows that the Clean Power 2030 (CP30)

target is 29GW, of which about 7GW have been constructed, 34GW have been

prioritised for connection by 2030 and 49GW have been prioritised for connection

by 2035.

There won’t be any new battery projects allowed until the current ones are ready

and the application window opens again.

All zones of the country are full. In the next phase, the most batteries will be in

North Wales, The Mersey, and The Humber.

2. 3. 4. 5. Based on the NESO connections reform, there seems to be no point in this application as

there is no need for it. Even if granted planning permission, it would not be connected to

the grid for at least 10 years.

3Paragraph 2.7 states that the landscape around the proposed site is fettered with other

energy infrastructure. The Development Plan comprises the North Devon and Torridge

Local Plan 2011-2031, of which Policy ST14: Enhancing Environmental Assets seeks

to protect and enhance the natural environment of North Devon by ensuring that

development contributes to protecting and enhancing local landscape character. The

proposed BESS with all its industrial containers and other infrastructure would neither

protect nor enhance the local landscape characture. Just because the surrounding

landscape is fettered with other energy infrastructurere is no justification for this proposal.

It is claimed that, due to the lack of intervisibility with the many other renewable energy

and infrastructure developments in the surrounding area and that other schemes are

never present in the same viewpoint, the cumulative impact is very low. However this

ignores the fact that when travelling around the district, the plethora of developments

become a dominant feature of the landscape.

In conclusion:

1. 2. 3. The application contains many misleading, incorrect and unsupported

statements which should be corrected before the application is determined.

There is no need for the proposed BESS since it would not get a grid connection for

at least 10 years.

The proposed BESS is counter to North Devon and Torridge Planning Policy ST14

as it would neither protect nor enhance the local landscape character.

The planning application should be refused.



More than 40 objections to huge battery storage site in Torridge

Devon's branch of the Campaign to Protect Rural England says it is worried about the proposals

 


 

 

Devon's CPRE says it will be opposing plans for a new battery storage installation at Alverdiscott in the Torridge district.

The application for a 99.4MW site with associated works, has already attracted more than 40 objections

 

 

The Campaign to Protect Rural England says 'there is no need' for it as the site would not be connected to the grid for at least 10 years, according to current data from the National Energy System Operator

 

The charity says that siting a battery installation with at least 50 industrial containers on land at Woodtown, East The Water, would neither ‘protect nor enhance the local landscape character’ and is counter to North Devon and Torridge planning policy.

Devon CPRE's Steve Crowther said: "There’s a growing cluster of solar farms and battery schemes around Alverdiscott and Stony Cross and local residents say ‘enough is enough’.

"They already have a fight on their hands, having formed the Bulworthy Solar Action Group in September 2025 to oppose plans for the largest solar farm and BESS scheme in Devon to date - 279 acres that would straddle two planning districts, Torridge and North Devon."

He added: “Alverdiscott has become a honeypot for investors wanting to cash in on the ‘solar and battery gold rush’. This latest proposal, if it gets approval, combined with the Bulworthy Solar Farm and BESS application that local people are already fighting, would make this a mega solar and battery site.

“The applicant claims that, because the many other renewable energy and infrastructure developments in the surrounding area are never present in the same viewpoint, the cumulative impact is very low. However, this ignores the fact that when travelling around the district, the plethora of installations have become a dominant feature of the landscape.”

 

 

We need your consent to load the translations

We use a third-party service to translate the website content that may collect data about your activity. Please review the details in the privacy policy and accept the service to view the translations.